Essex Industrial Estate Road Resurfacing

Essex Industrial Estate

Road Resurfacing

Scroll
Case study

Project Overview

The resurfacing of a major access road serving a busy industrial estate in Essex required a phased approach to keep the road operational.

The existing carriageway surface had become heavily worn and cracked, creating an unattractive appearance and reducing the overall quality of the estate’s infrastructure.

Due to the road remaining operational throughout the works, careful planning and phased construction were required to minimise disruption to businesses and site users.

Pre-Road Resurface

The Challenge

The industrial estate remained fully operational throughout the project, requiring continuous vehicle access for staff, visitors and commercial traffic.

Key challenges included:

  • 3,200m² of carriageway resurfacing.
  • Live operational industrial estate.
  • Tight programme requirements.
  • Maintaining traffic flow throughout the works.
  • Coordinating large-scale planing and resurfacing operations.

A phased approach was required to ensure safe vehicle movements while allowing the works to progress efficiently.

Road Resurface Traffic

Our Solution

We developed a traffic management and construction programme that allowed the road to remain operational throughout the project.

Works included:

  • Planing off 50mm of existing asphalt surfacing down to the underlying concrete slab.
  • Traffic management implementation to facilitate phased construction.
  • Completion of all planing operations within a single day.
  • Resurfacing of approximately 3,200m² using 50mm SMA10 asphalt.
  • Surfacing works completed in two phases, one side of the carriageway at a time.
  • Final compaction and quality control inspections throughout the works.

This phased methodology enabled safe access to be maintained while ensuring efficient delivery of the programme.

Road Resurfacing Completion

The Results

The completed scheme transformed the appearance and functionality of the estate road network.

Benefits delivered included:

  • 3,200m² of newly resurfaced carriageway.
  • Improved ride quality and appearance.
  • Elimination of existing cracking and surface deterioration.
  • Continued site operation throughout the project.
  • Minimal disruption to businesses and site users.
  • Durable SMA10 surface designed for long-term performance.